InsightsMaritime

Sector Intelligence Report

Maritime

Where the sector is going, where the money is going, and the best plays for the next 12-24 months

Data as of
18 Nov 2026
Written for
suppliers to HII, Newport News, Electric Boat and the uncrewed vessel builders
Prepared by
Bastion Atlas

Key figures

  • $65.8BFY2027 shipbuilding request for 34 ships. FY2026: $27.2B enacted plus $17.9B of reconciliation money
  • 18 + 16Battle force ships and support ships in the FY2027 request
  • $71.6BGeneral Dynamics awards in Q3 2026 for 9 Virginia-class and 5 Columbia-class submarines
  • $86.2BHII backlog at Q3 2026, up from $55.7B a year earlier
  • 1.1 to 1.2Virginia-class boats built a year, against 2.0 bought
  • 30Medium uncrewed surface vessels ordered on 29 Sep 2026, about $40M each
  • 250,000Skilled workers shipbuilders and suppliers need to hire over the next decade
  • $200B+Cost of public shipyard modernization, with work running past 2080

Bottom Line

  • The money is large and mostly discretionary.

    The FY2027 shipbuilding request is $65.8B for 34 ships. FY2026 carried $27.2B in the regular appropriation plus $17.9B from the 2025 reconciliation law. About $5.6B of the FY2027 request is mandatory. Among the 4 largest weapon-system categories the Congressional Research Service tracks, shipbuilding has the smallest mandatory share, about 8%.

  • The orders are already placed.

    General Dynamics booked $42.1B for 9 Virginia-class Block VI boats and $29.5B for 5 Columbia-class boats in the third quarter of 2026. HII booked $32.4B of awards, holds $86.2B of backlog and says the awards secure about 90% of its expected shipbuilding revenue through 2030.

  • Capacity is the binding constraint.

    Virginia-class output runs at about 1.1 to 1.2 boats a year against 2.0 bought. Boats deliver about 4 years late on average. Shipbuilders and suppliers need about 250,000 hires in a decade, and the Navy has put first-year attrition at 50-60%.

  • Work is moving out of the 2 nuclear yards.

    HII credits its growth to higher throughput and increased outsourcing. Anduril and the Navy committed $6.6B to a new components yard in Maryland. The request holds $8.7B for the maritime industrial base and shipyards.

  • Uncrewed moved from experiment to serial buy.

    The Navy ordered 30 medium uncrewed surface vessels from 3 builders on 29 Sep 2026 through a recurring marketplace. HII’s Lionfish order book reached 175 vehicles in November 2026.

  • Best position for 2027-2028:

    Become outsourced capacity for Electric Boat and Newport News. Sell throughput: Automation, welding, inspection and workforce. Get into the uncrewed bill of materials now, while builders scale from prototypes to lots of 10.

1. Where the Sector Is Going

Submarines come first, the surface fleet plan is larger, and uncrewed vessels have moved to serial buys. The binding constraint is yard capacity, not orders.

Submarines first: The Navy’s top industrial priority

  • Priority: The Navy’s 30-year shipbuilding plan of 11 May 2026 says raising output to at least 1 Columbia-class and 2 Virginia-class boats a year “remains the top industrial base priority”. The Chief of Naval Operations told Congress the higher rate will be in place by 2032.
  • Reality: Virginia-class production has run at about 1.1 to 1.2 boats a year since 2022, against 2.0 procured (Congressional Research Service). The longer-term goal is 2.33 a year.
  • Schedule: The Congressional Budget Office testified in April 2026 that Virginia-class boats average about 4 years late against contract dates and that the carrier CVN-80 is 18 to 26 months late.
  • FY2027 request: Two Virginia-class boats at $13.82B plus $1.44B of mandatory industrial base incentives, and 1 Columbia-class boat at about $16.2B.
Exhibit 1The yards build 1.1 to 1.2 Virginia-class boats a year against 2 boughtVirginia-class attack submarines a year

Source: Congressional Research Service RL32418.

A larger and different surface fleet plan

  • Fleet size: The Navy has 291 battle force ships today against a statutory goal of 355. The plan reaches 355 crewed ships by FY2040.
  • Battleship: A class of 15 ships over 30 years. The first 3, in FY2027 to FY2031, are priced at $43.5B. The Congressional Budget Office (August 2026) puts the program at about $275B in 2026 dollars and the first ship at about $23B. The administration asked for $1B of advance procurement in FY2027. The continuing resolution left it out and the Senate committee authorization bill removes it. The House appropriations bill keeps it.
  • Frigate: The FF(X) lead ship is requested in FY2027 at $1.64B. The Constellation class was cancelled.
  • Amphibious and landing ships: One America-class ship ($4.05B), 1 San Antonio-class ship ($2.73B) and 6 Medium Landing Ships. The landing ships are funded through the mandatory request: $1.70B for the 6 ships, or $1.89B with development. The Navy runs the program through a vessel construction manager, TOTE Services, under a contract worth up to $2.2B awarded in July 2026.
  • Destroyers: One DDG-51 requested at $3.28B, plus $0.31B in the mandatory request. The House bill and the Senate committee bill both authorize 2.
  • Scale: Forecast International estimates the plan implies about $39.6B a year of new construction and about $1.2T over 30 years, against about $30B a year and $900B in the prior plan.
Exhibit 2Submarines take almost half of the FY2027 shipbuilding requestFY2027 shipbuilding request by program, discretionary against mandatory ($B)

Source: Congressional Research Service R49023. Note: Quantities in brackets. Mandatory amounts too small to see: Columbia-class $0.21B, Ford-class $0.04B, carrier refueling $0.03B. The Medium Landing Ship line includes development.

Uncrewed vessels: From prototypes to lots of 10

  • New buying model: On 26 Mar 2026 the Navy cancelled its prior medium uncrewed surface vessel program and opened a recurring marketplace for production-ready designs, with the vendor carrying development risk. Seven designs went to at-sea evaluation in May 2026.
  • First lots: On 29 Sep 2026 the Navy awarded production agreements to Galliano Marine Services, HII and Saronic for 10 vessels each, 30 in total at an average of about $40M. First deliveries are due before the end of FY2027. A second call for solutions had gone out the week before.
  • Target: Grow the uncrewed surface fleet in the Indo-Pacific from 4 to 30 by 2030. The 2025 reconciliation law provided $2.1B for medium uncrewed surface vessels. The FY2027 request adds $427M for 3 more.
  • Undersea: HII received an order for 82 more Lionfish small uncrewed undersea vehicles in November 2026, taking the total to 175. Fifty had been delivered by 21 Oct 2026. The 5-year contract has the potential to reach 200 vehicles and more than $347M. Anduril’s Dive-XL was selected in March 2026 for the Combat Autonomous Maritime Platform. The FY2027 request holds $0.58B for uncrewed undersea vehicles, all of it discretionary. The House bills carry $0.61B and the Senate committee bill $0.84B.

Distributed shipbuilding: New yards, new owners

  • Arsenal-2 (6 Oct 2026): Anduril will invest $3.7B of private capital in a yard at Sparrows Point, Maryland, to build components and large assemblies for Virginia-class submarines. The Navy contract is worth up to $2.9B, with payments tied to demonstrated production outcomes. The company plans to break ground by early 2027 and start operations in 2030, with about 3,100 direct jobs. The President said taxpayers receive a 40% stake. The company says the stake is in the new subsidiary that will operate the yard.
  • Hadrian: Opened a $2.4B facility in Cherokee, Alabama in March 2026, partly funded by the Navy, to make parts for Columbia-class and Virginia-class submarines.
  • Saronic: Raised $1.75B at a $9.25B valuation on 31 Mar 2026. It chose Brownsville, Texas in July 2026 for a $3.2B shipyard and committed $300M to expand its Franklin, Louisiana yard.
  • Automation: HII is piloting mechanized automated welding with HD Hyundai Heavy Industries.

2. Where the Money Is Going

Most of the shipbuilding money is discretionary and much of it is already under contract. The industrial base funds that would ease the bottleneck sit mostly in the unfunded mandatory request.

Exhibit 3Industrial base money is requested in several pots, most of them mandatoryIndustrial base lines in the FY2027 request and the House bill
AmountLineFunding type
$8.7BMaritime industrial base and shipyard infrastructure: 7 private yards, 4 public yards, Tier 2 yards and site planning for a 5th public shipyardFY2027 request
$1,850MAdvanced shipbuilding industrial base and future ship experimentationMandatory request
$1,655MSurface Ship Maritime Industrial BaseMandatory request
$1,440MVirginia-class industrial base incentivesMandatory request
$206MSubmarine Maritime Industrial Base: Supplier development $125M, workforce $78M, shipyard infrastructure $3MMandatory request
$828MSubmarine industrial baseHouse appropriations committee bill

Source: Department of War FY2027 budget overview, Department of War FY2027 Mandatory Funding Overview, Congressional Research Service R49023, House Appropriations Committee. Note: Lines come from different documents and are not additive. Mandatory lines need a reconciliation law.

Exhibit 4HII and General Dynamics booked more than $100B of awards in a single quarterThird-quarter 2026 results
CompanyRevenueAwards and backlogSignal for suppliers
HII$3.5B, up 10.8%. Newport News $1.91B, up 18.1%. Ingalls $876M, up 5.8%.Awards $32.4B. Backlog $86.2B, against $55.7B a year earlier.Shipbuilding revenue guidance raised to $10.5-10.7B at a 6.0-6.5% margin. Throughput up about 9% in the year to date. Growth credited to throughput and outsourcing. Awards cover about 90% of expected shipbuilding revenue through 2030.
General Dynamics$14.6B, up 12.9%. Marine Systems $4.96B, up 21.1%.Orders $98.8B. Backlog $220.3B, about double a year earlier. Marine Systems backlog $146.9B.Marine Systems margin 7.9%. Funded backlog is $111.8B, which leaves about $108.5B not yet funded.

Source: Company results, 29-30 Oct 2026.

Exhibit 5Plan against 3 funding cases, not 1FY2027 funding cases and what each means for this sector
CaseWhat it takesWhat it means for this sector

A. Full request

$1.15T discretionary plus $350B mandatory

A new reconciliation law before the 120th Congress convenes on 3 Jan 2027. Senate Republicans urged one on 10 Nov 2026. Budget analysts rate it unlikely in the lame-duck session.All 34 ships: 18 battle force ships and 16 support ships. The 6 Medium Landing Ships and the mandatory industrial base lines in Exhibit 3 are funded.
B. Base plus a small reconciliationRegular appropriations near the House committee bill (about $1.072T), plus a smaller reconciliation package that adds no more than $60B to deficits over FY2027 to FY2036, the limit the House-passed budget resolution gives the Armed Services Committee. The Senate has not voted on its version.Most of the program survives because about 92% of the selected programs the Congressional Research Service tracks are discretionary. Appropriators decide the battleship advance procurement and the 2nd DDG-51. Mandatory-only lines (Medium Landing Ship, submarine incentives, surface industrial base) need discretionary adds or fall away.
C. Extended continuing resolutionThe continuing resolution that expires 11 Dec 2026 is extended into 2027. FY2026 rates apply. Absent a specific exception, the law bars new starts, production-rate increases and new multiyear procurements that use advance procurement funding for economic-order-quantity buys. The FY2027 budget documents list more than 150 new starts.Absent a specific exception, new starts wait. The FF(X) lead ship and the battleship are the most exposed. Contracted submarine and carrier work continues. Supplier cash flow on new programs moves right.

Source: Bastion Atlas planning constructs built on the public record (P.L. 119-103, H.R. 9495, H. Con. Res. 113). Note: The cases are not probability forecasts.

Allied and private capital

  • South Korea: Directed $150B of a $350B investment commitment to US shipbuilding. Hanwha plans $5B for its Philadelphia yard. It was selected in July 2026 to build range instrumentation vessels for the Missile Defense Agency. TOTE Services, the Navy’s vessel construction manager, announced on 30 Oct 2026 that it had selected Hanwha Defense USA to build 1 Medium Landing Ship at the Philadelphia yard for $269M, with options for 3 more. It is Hanwha’s first contract to build a Navy ship. HD Hyundai and Kiewit formed a joint venture to develop a new US shipyard.
  • Australia: Pledged US$3B to the US submarine industrial base under AUKUS.
  • Private capital: Anduril ($3.7B at Sparrows Point) and Saronic ($3.2B in Brownsville plus $300M in Franklin) are funding yards ahead of orders. Hadrian’s $2.4B Alabama facility is partly Navy-funded.
  • Federal credit: The Office of Strategic Capital names the maritime industrial base as a priority sector for its loan program. The $20B of credit subsidy requested for that program sits in the mandatory request and is not funded.

3. Geopolitics and Policy

The Indo-Pacific sets the requirement, allies are bringing capital, and Congress has not settled how much work foreign-owned yards may do.

  • Indo-Pacific: The plan grows the attack submarine force from 47 in FY2027 to 56 in 2040 and 68 in 2056, and puts 30 uncrewed surface vessels in the theater by 2030.
  • AUKUS: The US review concluded in December 2025 in favor of proceeding. Submarine Rotational Force-West stands up at HMAS Stirling by 2027. Australia is to acquire 3 in-service Virginia-class boats, which adds to the demand on US output.
  • Foreign yards: A presidential memorandum lets foreign companies that invest in US yards build up to 2 ships in their home yards. The Senate committee authorization bill would allow up to 2 bulk fuel or sealift vessels to be built abroad when tied to investment in the US maritime base, and bars foreign work on warships. The outcome is open in conference.
  • Oversight: House Armed Services is expected to examine government equity deals in the new Congress. The public stake in Arsenal-2 falls in that category.
  • Public yards: The Government Accountability Office (GAO-26-107830, 25 Sep 2026) found the program to modernize the 4 public shipyards will exceed $200B and run past 2080. The 2018 estimate was about $21B over 20 years.
  • Workforce: The Navy Secretary said in January 2026 that shipbuilders and suppliers need to hire about 250,000 skilled workers over the next decade and that a quarter of the shipyard workforce is retirement-eligible within 5 years. Navy testimony in March 2025 put first-year attrition at 50-60%. Wage increases at Electric Boat and Newport News met the 2025 hiring rate and cut attrition by 2 to 5 points, according to the May 2026 plan.
  • Materials and trade: Section 232 duties on steel stay at 50%. The DFARS restriction on magnets, tungsten and tantalum extends to the full supply chain on 1 Jan 2027.
  • Iran war: The Navy’s weapons procurement request is $22.6B. The war drew down cruise missile and Standard Missile stocks, and munitions compete with ships inside the same Navy topline.

4. Competitive Landscape

The 2 nuclear yards hold the orders. Competition is among suppliers for outsourced scope, and among new yards for component, module and uncrewed work.

Exhibit 6The openings are in outsourced scope, new yards and uncrewed vesselsSegments, players, latest markers and openings for suppliers
SegmentPlayersLatest markerOpening for suppliers
Nuclear submarinesGeneral Dynamics Electric Boat, HII Newport News$71.6B of awards at General Dynamics in Q3 2026Outsourced modules, machining, castings, valves and pipe
Surface combatants and amphibious shipsHII Ingalls and the other surface yardsFF(X) lead ship, 1 America-class ship and 1 San Antonio-class ship in the requestStructural units and outfitting. Ingalls reports a slower labor recovery.
New-model yardsAnduril, Saronic, Hadrian$6.6B Arsenal-2. $3.2B Brownsville yard.Equipment, tooling and construction-phase supply before 2030
Medium uncrewed surface vesselsGalliano Marine Services, HII, Saronic. Seven designs reached at-sea evaluation.30 vessels at about $40M eachPropulsion, power, autonomy, payload integration
Uncrewed underseaHII, Anduril175 Lionfish on order. Dive-XL selected in March 2026.Batteries, sensors, composite structures
Allied entrantsHanwha, HD Hyundai$5B Philadelphia plan. First contract to build a Navy ship, announced on 30 Oct 2026 by the Navy’s vessel construction manager.A US-content supply base for foreign-owned yards
Maintenance technologyRobotics and inspection firmsA Navy inspection-robotics contract ceiling rose from $71M to $300M in October 2026Tools that return ships to the fleet faster

Source: Contract announcements and company results. Note: The openings column is Bastion Atlas assessment.

  • The 2 nuclear yards are sold out. Electric Boat and Newport News hold the work. The competition is among suppliers for outsourced scope, and among new yards for component and module work.
  • Venture-backed builders compete on speed and private capital. Saronic won a place in the first uncrewed surface vessel lots 6 months after closing its $1.75B round.
  • Ceilings are not orders. Contract ceilings signal intent. Obligated dollars follow task orders. Suppliers to newer vendors should plan against obligations.

5. Best Plays for the Next 12-24 Months

The 7 plays below follow the money that is already contracted or least exposed to the funding fight. Each rests on the evidence in Sections 1 to 4.

Exhibit 7Seven plays for shipbuilding suppliers and uncrewed vessel buildersWhat to do, why the evidence supports it, and the first move
PlayWhy now (the evidence)Move in the next 90 days
  1. 1. Become outsourced capacity for the 2 nuclear yards

    Window: Now to 2032

    Why now (the evidence)

    • Output of 1.1 to 1.2 boats a year against 2.0 bought
    • New submarine awards of $71.6B at General Dynamics in 1 quarter
    • HII credits growth to throughput and outsourcing
    • Virginia-class incentives of $1.44B requested, and $828M for the submarine industrial base in the House bill

    Move in the next 90 days

    • Build a capacity package: Floor space, weld and inspection certifications, open hours
    • Take it to Electric Boat and Newport News supplier development teams
    • Ask for industrial base funding to cover capital equipment
  2. 2. Sell throughput, not parts

    Window: Now to 2028

    Why now (the evidence)

    • Boats deliver about 4 years late
    • HII throughput up about 9% and a welding automation pilot under way
    • The Arsenal-2 contract pays on demonstrated production outcomes
    • Public yard modernization now exceeds $200B and runs past 2080

    Move in the next 90 days

    • Package automation, inspection and digital work instructions as schedule recovery
    • Offer outcome-based pricing on a pilot
    • Prove it at a Tier 2 yard or supplier first
  3. 3. Get into the uncrewed bill of materials at lot 1

    Window: Now to 2030

    Why now (the evidence)

    • Thirty vessels ordered from 3 builders at about $40M each
    • The marketplace is recurring and buys production-ready designs
    • Fleet target of 30 in the Indo-Pacific by 2030
    • Lionfish order book of 175

    Move in the next 90 days

    • Target Galliano, HII and Saronic, plus the other designs that reached at-sea evaluation
    • Offer subsystems that are already in production
    • Quote for lots of 10 with firm delivery dates
  4. 4. Supply the new yards while they are being built

    Window: 2026 to 2030

    Why now (the evidence)

    • Arsenal-2 plans to break ground by early 2027 and to open in 2030
    • Saronic: $3.2B in Brownsville and $300M in Franklin
    • Hanwha: $5B plan for Philadelphia

    Move in the next 90 days

    • Register as a supplier during the construction phase
    • Lead with equipment, tooling, automation and factory software
    • Tie offers to the local hiring commitments each project has made
  5. 5. Solve the workforce problem for a customer

    Window: Now to 2030

    Why now (the evidence)

    • About 250,000 hires needed in a decade
    • First-year attrition put at 50-60% in Navy testimony
    • Wage increases cut attrition by 2 to 5 points at the nuclear yards
    • The mandatory request lists $78M for submarine workforce and $125M for supplier development

    Move in the next 90 days

    • Offer training pipelines and retention programs with measured results
    • Position automation as a way to cut skilled hours per unit
    • Seek industrial base funding jointly with a yard
  6. 6. Hedge with allied programs

    Window: 2027 to 2029

    Why now (the evidence)

    • Australia pledged US$3B and hosts rotational submarines from 2027
    • South Korea directed $150B to US shipbuilding, and Hanwha’s first contract to build a Navy ship was announced on 30 Oct 2026
    • Foreign-yard limits are unresolved in the authorization bills

    Move in the next 90 days

    • Qualify for AUKUS supply chains
    • Build relationships with Hanwha and HD Hyundai procurement in the US
    • Track the conference outcome on foreign-yard limits
  7. 7. Weight the pipeline for a continuing resolution

    Window: Next 6 months

    Why now (the evidence)

    • The continuing resolution expires 11 Dec 2026 and, absent a specific exception, bars new starts
    • The battleship advance procurement was left out of the continuing resolution and removed in the Senate committee bill
    • The Congressional Budget Office prices the battleship program at about $275B
    • House Armed Services is expected to examine government equity deals

    Move in the next 90 days

    • Base the 2027 plan on submarines, destroyers, amphibious ships and sustainment
    • Treat the battleship and frigate as options until appropriated
    • Keep bids ready so you can move when a new start is released

Source: Evidence items are facts from the public record as of 18 Nov 2026. Note: The plays are Bastion Atlas analysis.

6. Dates to Watch

Exhibit 8Two decision points fall inside 60 days. Capacity targets run to 2032 and beyondDecision path for maritime suppliers (not to scale)

Source: Public laws, the 30-year shipbuilding plan and company announcements listed in Exhibit 9.

Exhibit 9Decision points through 2040What happens, and why it matters to a supplier
DateEventWhy it matters
11 Dec 2026Continuing resolution (P.L. 119-103) expiresA further extension keeps FY2026 rates and, absent a specific exception, the section 102 bar on new starts, production-rate increases and certain new multiyear procurements.
1 Jan 2027DFARS 252.225-7052 extends to the full supply chainThe sourcing restriction on samarium-cobalt and neodymium-iron-boron magnets, tungsten and tantalum from China, Russia, Iran and North Korea reaches back to mining and refining, at every contract tier. Exceptions include certain commercial off-the-shelf items and nonavailability waivers.
By 3 Jan 2027Last window for a reconciliation law in the 119th CongressDecides whether any of the $350B mandatory request is funded. The House-passed budget resolution limits the Armed Services Committee to $60B of added deficits over 10 years. The Senate has not voted on its version.
3 Jan 2027120th Congress convenes with Democratic majorities in both chambersNew chairs at House and Senate Armed Services (Adam Smith, Jack Reed). Expected oversight topics at House Armed Services: Golden Dome, munitions stockpiles and government equity deals.
By 1 Feb 2027 (statutory date)FY2028 President’s Budget dueShows whether the $65.8B shipbuilding level and the battleship carry forward.
By early 2027 (company plan)Arsenal-2 groundbreaking at Sparrows PointStart of construction-phase procurement.
2027Submarine Rotational Force-West stands up at HMAS StirlingAUKUS sustainment demand begins in Australia.
By 30 Sep 2027First medium uncrewed surface vessels due for deliveryFirst test of the marketplace model at production scale.
2030Arsenal-2 initial operations. Thirty uncrewed surface vessels in the Indo-Pacific.Tests whether distributed shipbuilding and the marketplace delivered.
2032Navy target for the higher submarine rate: 1 Columbia-class and 2 Virginia-class a yearThe date supplier capacity has to be in place.
FY2040Goal of 355 crewed battle force shipsLong-range demand anchor in the 30-year plan.

Source: Public laws, the 30-year shipbuilding plan, Navy and company announcements.

What would change this view

  • Upside: Appropriators funding the 2nd DDG-51 and the industrial base lines in the regular bill.
  • Downside: A full-year continuing resolution that delays the FF(X) lead ship and other new starts.
  • Watch: Virginia-class deliveries per year, the conference outcome on foreign-yard limits, and the next round of the uncrewed vessel marketplace.

About This Report

  • Scope: US naval shipbuilding and repair, uncrewed surface and undersea vessels, and the allied capital entering US yards. Data cut-off: 18 Nov 2026.
  • Evidence base: Department of War FY2027 budget documents, the Navy’s 30-year shipbuilding plan, Congressional Research Service, Congressional Budget Office and Government Accountability Office reports, the FY2027 defense authorization and appropriations bills, third-quarter 2026 results from HII and General Dynamics, Navy contract announcements, company announcements from Anduril, Saronic, Hadrian and Hanwha, and Forecast International analysis. SONAR’s continuously updated intelligence layer was the signal source, through the 46 SONAR reports issued between 30 Aug and 18 Nov 2026.
  • Verification rule: Every figure met 1 of 2 tests before use. It was read from the primary document where that document is public, or it was confirmed in at least 2 independent accounts of an official announcement or company statement. Headline figures were then checked a second time against the source. This edition also reflects an independent line-by-line fact check, with each challenge tested against the primary document before any change was made. Figures that failed a pass were corrected or removed.
  • Request is not appropriation: Unless marked as enacted, FY2027 figures are the President’s Budget request of 3 Apr 2026. Mandatory figures depend on a reconciliation law that has not been passed.
  • Company figures: Backlog, guidance, targets and framework agreements are as stated by the companies. Framework agreements remain subject to congressional authorization and appropriations.
  • Analysis: The “Bottom Line”, section lead-ins, “So what” notes, planning cases and plays are Bastion Atlas judgment built on the facts above.

Key public documents behind the figures

  1. Department of War, FY2027 Budget Request briefing and Overview Book (April 2026)
  2. Department of War, FY2027 Mandatory Funding Overview
  3. Congressional Research Service, R49023 (FY2027 request for selected weapon systems)
  4. P.L. 119-103, Continuing Appropriations and Extensions Act, 2027 (Division A, section 102)
  5. House Appropriations Committee, FY2027 defense bill summaries (June 2026, H.R. 9495)
  6. H.R. 8800 and S. 4784 (FY2027 defense authorization bills) and H. Con. Res. 113 (House budget resolution)
  7. Department of the Navy, FY2027 30-year shipbuilding plan (11 May 2026)
  8. Congressional Research Service, RL32418 (Virginia-class submarine program)
  9. Congressional Budget Office, shipbuilding testimony (April 2026) and battleship cost analysis (August 2026)
  10. Government Accountability Office, GAO-26-107830 (public shipyard modernization, 25 Sep 2026)
  11. HII, third-quarter 2026 results (29 Oct 2026)
  12. General Dynamics, third-quarter 2026 results (30 Oct 2026)
  13. Department of the Navy, medium uncrewed surface vessel production awards (29 Sep 2026)
  14. White House and Anduril, Arsenal-2 announcement (6 Oct 2026)
  15. HII, Lionfish production order announcement (November 2026)
  16. Saronic, Series D (31 Mar 2026) and Brownsville shipyard announcements (2026)
  17. Hanwha, Philadelphia shipyard plan (August 2025), and TOTE Services, Medium Landing Ship shipyard selection announcement (30 Oct 2026)
  18. Secretary of the Navy, remarks on the shipbuilding workforce (January 2026)
  19. Forecast International, analysis of the 30-year shipbuilding plan (May 2026)
  20. Department of War, FY2027 budget justification for the Office of Strategic Capital loan program (April 2026)

Intelligence built for your business

This report covers the sector. SONAR covers your business: Opportunity and intelligence briefs every week, 100% tailored to your products & services.