1. Where the Sector Is Going
Three ramps are landing on a single supply base, and capacity, not orders, now sets the pace.
Demand: Three ramps on a single supply base
| System | Baseline | Framework target | Agreement |
|---|---|---|---|
| PAC-3 MSE | About 600 a year (620 delivered in 2025) | About 2,000 a year by 2030 | 7-year framework signed 6 Jan 2026, with 7-year subcontracts to key suppliers. Multiyear contract of about $58.6B for FY2026 to FY2032, after a $53.86B modification on 29 Jul 2026. |
| THAAD interceptor | 96 a year | 400 a year | Framework of 29 Jan 2026. An undefinitized contract action of $35B followed in June 2026. |
| Tomahawk | Not stated | More than 1,000 a year | RTX framework, February 2026 |
| AMRAAM | Not stated | At least 1,900 a year | RTX framework, February 2026 |
| SM-6 | Not stated | More than 500 a year | RTX framework, February 2026 |
| SM-3 IB and IIA | Not stated | Up to 4 times current output | RTX framework, February 2026 |
| PAC-3 seeker | Up to 750 a year under a $2.7B award of October 2025 | Triple output over 7 years | Boeing framework, 1 Apr 2026 |
| PAC-3 and THAAD propulsion | Not stated | Nearly triple for PAC-3. Quadruple for THAAD. | L3Harris: 2 frameworks of 7 years each on 27 Jul 2026, plus a $1B government investment in its missile business |
Source: Company and Department of War announcements. Note: All frameworks are subject to congressional authorization and appropriations.
Source: Company and Department of War announcements. Note: Targets as announced. Baselines shown where stated.
- Commercial aerospace: CFM delivered 1,565 LEAP engines in the first 9 months of 2026, up 26%. Boeing targets 52 737s a month in the back half of 2027. Airbus targets 70-75 A320-family aircraft a month by end-2027.
- Shipbuilding: HII credits growth to throughput and outsourcing. Anduril and the Navy committed $6.6B to a submarine components yard that is planned to open in 2030.
- Combined effect: Commercial aerospace, missiles and shipbuilding are pulling on the same castings, forgings and electronics at the same time, which removes the counter-cyclical relief suppliers normally get.
Supply: Capacity, not orders, sets the pace
- Bottlenecks: In a Roland Berger survey of 95 European aerospace companies in early 2026, 55% still reported sizable supply-chain issues. Pain points: Forgings, electronic components, fasteners, test and surface-treatment lead times, and experienced staff.
- Programs: In a 2026 Bain review of 15 US and European aerospace and defense programs, 87% said supply-chain issues outweigh labor, engineering or capital equipment as a constraint. Production growth targets run 20% to 500% above the levels set between 2024 and early 2026.
- Lead times: BCG measured titanium at about 9 months and one key steel alloy at 70-80 weeks in 2024.
- Labor: Attrition ran at about 15% in 2024 (Aerospace Industries Association workforce study). Deloitte and the Manufacturing Institute estimate US manufacturing needs 3.8M workers from 2024 to 2033 and that up to 1.9M positions could go unfilled.
New model: The factory as the product
- Hadrian: Raised $1.37B on 6 Aug 2026 at a $7.87B valuation. Slightly under 3M square feet across 4 sites. Customers include Lockheed Martin, RTX and Anduril. A December 2025 agreement covers a factory-as-a-service cell at a Lockheed Martin missiles site for PAC-3 MSE, THAAD, PrSM and GMLRS parts. A $2.4B facility in Alabama, partly Navy-funded, makes submarine parts.
- Anduril: Arsenal-1 in Ohio is planned at 5M square feet. Arsenal-2 in Maryland carries $3.7B of private capital and a Navy contract of up to $2.9B.
- Primes: Lockheed Martin broke ground on a munitions acceleration center in Camden, Arkansas on 30 Jan 2026.
Consolidation: A record deal year
- Volume: White & Case and Mergermarket recorded 65 defense deals worldwide in the first 9 months of 2026, more than in all of 2025 and the most in data going back to 2018. Combined value was $7B. Third-quarter deal value was $4.2B, against $0.6B a year earlier.
- Capital: Preqin counts 621 private-capital deals worth $24.4B in aerospace and 90 worth $6.1B in defense in 2025.
- Vertical integration: GE Aerospace agreed in October 2026 to buy castings maker Consolidated Precision Products.
2. Where the Money Is Going
Washington wants to finance capacity, but most of that money is requested, not appropriated. Prime and private capital is what is moving today.
| Category | Request | Manufacturing content |
|---|---|---|
| Defense industrial base | $113,105M | Loans, purchase commitments, supplier investments, critical minerals |
| Next-generation technology and autonomy | $102,500M | Drone Dominance ($53.6B) and sovereign AI infrastructure ($46.0B) |
| Munitions | $47,022M | Includes $19,564M to close FY2026 procurement gaps on 12 critical munitions |
| Barracks and facilities | $36,038M | Construction |
| Homeland defense and Golden Dome | $17,528M | Golden Dome fund of $17,121M |
| Air superiority | $14,430M | 53 F-35s, sustainment, modifications, 7 KC-130Js |
| Space superiority | $11,725M | Space-based sensing and data transport |
| Maritime superiority | $7,654M | Shipyard, supplier and submarine industrial base investments |
Source: Department of War FY2027 Mandatory Funding Overview. Note: Categories sum to $350.0B. None of it is available without a reconciliation law.
Source: Department of War FY2027 Mandatory Funding Overview. Note: Lines total $113.1B.
- Defense Production Act purchases ($23.6B): Loans, purchase commitments and incentives for kinetic weapons, castings and forgings, microelectronics and battery components.
- Industrial Base Analysis and Sustainment ($16.3B): Munitions and solid rocket motor sub-tier suppliers, critical chemicals, workforce, energy storage and microelectronics.
- Office of Strategic Capital ($20.0B): Credit subsidy for the office’s direct loans. The budget justification assumes an average subsidy rate of about 10%, so the $20B would support about $200B of loans. The 2025 reconciliation law (P.L. 119-21) provided $500M of subsidy for up to $100B of loans, loan guarantees and technical assistance for critical minerals, and $1B for up to $100B for covered technologies. Both run through 30 Sep 2029. Priority sectors named are the maritime industrial base, critical minerals and drone technology.
- Critical minerals ($48.7B): Includes $18.0B for the National Defense Stockpile.
Source: Department of War FY2027 Mandatory Funding Overview, House Appropriations Committee bill summary. Note: The $59.9B is the sum of the 3 mandatory lines: $23.6B, $20.0B and $16.3B.
- Reality check: The House appropriations bill provides a little over $2.9B for the 3 tools combined. It also provides $10.6B for critical munitions with multiyear authority, per the subcommittee summary, and $836M for low-cost munitions. The House-passed budget resolution would let the Armed Services Committee add no more than $60B to deficits over FY2027 to FY2036 through reconciliation. The Senate has not voted on its version.
| Case | What it takes | What it means for this sector |
|---|---|---|
A. Full request $1.15T discretionary plus $350B mandatory | A new reconciliation law before the 120th Congress convenes on 3 Jan 2027. Senate Republicans urged one on 10 Nov 2026. Budget analysts rate it unlikely in the lame-duck session. | The industrial base tools are funded at scale. Loan and purchase-commitment programs open to sub-tier suppliers. Framework agreements convert to funded multi-year contracts. |
| B. Base plus a small reconciliation | Regular appropriations near the House committee bill (about $1.072T), plus a smaller reconciliation package that adds no more than $60B to deficits over FY2027 to FY2036, the limit the House-passed budget resolution gives the Armed Services Committee. The Senate has not voted on its version. | Industrial base tools stay near the $2.9B in the House bill. Munitions get priority inside a smaller package. Primes and private investors carry most of the capacity investment. |
| C. Extended continuing resolution | The continuing resolution that expires 11 Dec 2026 is extended into 2027. FY2026 rates apply. Absent a specific exception, the law bars new starts, production-rate increases and new multiyear procurements that use advance procurement funding for economic-order-quantity buys. The FY2027 budget documents list more than 150 new starts. | Absent a specific exception, production-rate increases wait, and so do new multiyear procurements that use advance procurement funding for economic-order-quantity buys. Framework ramps risk stalling near current rates until an appropriation passes. Suppliers that invested ahead of orders carry the cost. |
Source: Bastion Atlas planning constructs built on the public record (P.L. 119-103, H.R. 9495, H. Con. Res. 113). Note: The cases are not probability forecasts.
| Source | Commitment | Meaning for suppliers |
|---|---|---|
| Lockheed Martin | Agreed to invest at least $7B in F-35 initiatives. Backlog includes $52.5B for PAC-3 MSE. | Multi-year volume to flow down. Cost pressure comes with it. |
| Northrop Grumman | About $2.5B committed to B-21 production capacity. | Capacity additions through 2027. |
| RTX | Backlog of $340B. More than $81B of commercial and defense awards in the third quarter of 2026, nearly $59B of it defense. | Tomahawk, AMRAAM and Standard Missile sub-tier demand. |
| Government as investor | An investment of $1B in L3Harris’s missile business. A stake in the company that will operate Arsenal-2, put at 40% by the President. | A new source of capital that brings oversight with it. |
| Venture and growth capital | Hadrian $1.37B. Anduril $5B at a $61B valuation. | New entrants can buy equipment and talent faster than incumbents. |
Source: Company announcements and results, January to November 2026.
3. Geopolitics and Policy
The Iran war made munitions the first call on industry, and 2 compliance dates in January 2027 change what a supplier can ship.
The Iran war made munitions the first call on industry
- Draw-down: The Congressional Budget Office (15 Sep 2026) estimates $21.7B to replace expended munitions: $13.1B for interceptors, $7.3B for land-attack cruise missiles and $1.2B for other munitions.
- Duration: The US used an estimated one-half to two-thirds of certain interceptor inventories since June 2025. Rebuilding takes at least 5 years, even at higher rates. That makes interceptor demand durable across election cycles.
- Unfunded replacement: The FY2026 supplemental request of nearly $70B, which includes $21B to speed munitions buys and expand production lines, has not been enacted.
Critical materials: Two dates in January
- 1 Jan 2027: The DFARS 252.225-7052 restriction extends to the full supply chain, from mine to magnet, for neodymium-iron-boron and samarium-cobalt magnets, tungsten and tantalum from China, Russia, Iran and North Korea. It applies to prime contracts and subcontracts at any tier. It is not a blanket ban: Exceptions include certain commercial off-the-shelf items and nonavailability waivers.
- Executive Order 14415 (20 Jul 2026): Restricts waivers under the sourcing statute. Directs the Secretary to issue supply-chain mapping guidance within 180 days, by about 16 Jan 2027, and regulations within 90 days after that. No mapping duty binds contractors until those rules arrive. The order also calls for qualifying alternative sources of supply.
- 10 Jan 2027: China’s suspension of its October 2025 export controls ends unless extended again. Its April 2025 license controls on 7 medium and heavy rare earths remain in force. On 22 Jun 2026 China added 10 US firms to its control list.
- Concentration: China holds about 90% of rare-earth processing and more than 90% of magnet production.
Tariffs and metals
- Section 232: Steel and aluminum duties stand at 50%. Since April 2026 a flat 50% applies to articles made almost entirely of steel, aluminum or copper and 25% to derivative products.
- Content rule: A proclamation of 1 Jun 2026 lowered the US-content threshold from 95% to 85% and added derivative products.
Cybersecurity: A pause, not a repeal
- Status: Phase I of CMMC (self-assessment) has applied since 10 Nov 2025. On 13 Jul 2026 the Department of War suspended Phase II, the third-party Level 2 certification that was due on 10 Nov 2026, pending a task force review. As of late October 2026 no new date had been set.
- Still required: DFARS 252.204-7012, NIST SP 800-171 and scores in the Supplier Performance Risk System. Primes may still flow down Level 2.
- Cost: The Small Business Administration estimates third-party certification can cost a small contractor almost $600,000. The Senate committee bill would create grants to help small and nontraditional firms reach Level 2.
Congress
- Open items in the FY2027 authorization bills: Multiyear authority for munitions (13 programs in the House bill, 19 in the Senate bill), right-to-repair, and Senate limits on stock buybacks and dividends.
- New majority: From 3 Jan 2027, House Armed Services is expected to pursue munitions stockpiles and government equity deals, and may review reliance on a small number of vendors.
4. Competitive Landscape
Suppliers now compete with, and sell to, primes that invest their own capital, software-defined manufacturers, vertical integrators and sponsor-backed consolidators.
| Archetype | Public examples | What it means for Tier 1 and below |
|---|---|---|
| Primes investing their own capital | Lockheed Martin, Northrop Grumman, RTX, L3Harris | Multi-year terms flow down. Dual-sourcing rises. Suppliers are expected to co-invest. |
| Software-defined manufacturers | Hadrian, Anduril | Compete for machining and assembly work. Also buy capacity and partner with specialists. |
| Vertical integrators | GE Aerospace buying a castings maker. Airbus absorbing structures work. | Fewer independent sources in bottleneck processes. Strategic buyers for the rest. |
| Sponsor-backed consolidators | Private capital closed 90 defense deals and 621 aerospace deals in 2025 | Scale competitors in special processes. An exit route for founder-owned firms. |
| Government as financier | Loans, purchase commitments and equity stakes | Capital for capacity, with reporting and oversight attached. |
Source: Public deal and company announcements, Preqin. Note: The assessment column is Bastion Atlas judgment.
Source: Company results. Note: Boeing and RTX totals include commercial aerospace.
5. Best Plays for the Next 12-24 Months
The 8 plays below favor money that is contracted or private over money that is requested. Each rests on the evidence in Sections 1 to 4.
1. Sign the multi-year subcontracts
Window: Now to mid-2027
Why now (the evidence)
- PAC-3 MSE moves from about 600 to about 2,000 a year under a 7-year framework
- Key suppliers are receiving 7-year subcontracts
- Seeker and propulsion frameworks triple or quadruple output
Move in the next 90 days
- Ask each prime for a framework-backed long-term agreement
- Negotiate capital recovery, price adjustment and termination protection
- Remember every framework is subject to appropriations
2. Keep a costed capacity project on file
Window: Next 90 days
Why now (the evidence)
- A request of $59.9B for 3 industrial base tools, against a little over $2.9B in the House bill
- Defense Production Act lines name castings, forgings, microelectronics and batteries
- The 2025 law set Office of Strategic Capital financing ceilings of up to $100B for critical minerals and up to $100B for covered technologies
Move in the next 90 days
- Write the project: Equipment, added output, jobs, schedule, cost share
- Brief the industrial base and strategic capital offices now
- Attach a demand letter from a prime
3. Trace restricted materials before 1 Jan 2027
Window: Before 1 Jan 2027
Why now (the evidence)
- The sourcing restriction on magnets, tungsten and tantalum reaches back to the mine on 1 Jan 2027
- Executive Order 14415 restricts waivers and starts a mapping rule, with guidance due by about 16 Jan 2027
- China holds about 90% of rare-earth processing
Move in the next 90 days
- Trace each restricted material to the mine and smelter
- Collect certifications from every tier and record which parts fall under an exception
- Qualify a compliant second source and hold buffer stock
4. Automate against a 15% attrition rate
Window: 2027
Why now (the evidence)
- Attrition of about 15%, more than double the US average
- Up to 1.9M manufacturing positions could go unfilled by 2033
- Investors value automated factories at multi-billion-dollar levels
Move in the next 90 days
- Target the operations with the most skilled hours per part
- Capture process knowledge in digital work instructions
- Tie automation spend to a rate commitment from a customer
5. Choose: Buyer or seller
Window: 2027 to 2028
Why now (the evidence)
- A record 65 defense deals recorded in 9 months
- Third-quarter deal value 7 times the prior year
- Primes are buying bottleneck suppliers
Move in the next 90 days
- If selling: Clean contracts, quality records and customer concentration
- If buying: Shortlist 3 targets in adjacent special processes
- Either way, know your value to a strategic buyer
6. Protect margin from metals and tariffs
Window: Now
Why now (the evidence)
- Section 232 duties at 50%, with 25% on derivative products
- US-content threshold lowered to 85%
- Long lead times on titanium and specialty steel
Move in the next 90 days
- Add raw-material and tariff pass-through to every agreement
- Review content calculations against the 85% threshold
- Secure domestic melt sources where they exist
7. Hold cyber readiness through the CMMC pause
Window: Now
Why now (the evidence)
- Phase II is suspended with no new date
- Phase I and DFARS 252.204-7012 still apply
- Primes may still flow down Level 2
- Certification can cost a small firm almost $600,000
Move in the next 90 days
- Keep your Supplier Performance Risk System score current and accurate
- Stay assessment-ready so a flow-down does not cost an award
- Watch for the Senate grant provision in the final authorization bill
8. Balance commercial and defense on purpose
Window: 2027
Why now (the evidence)
- Commercial backlogs are locked in and rates are rising
- Defense ramps depend on appropriations that are not passed
- Both draw on the same forgings, castings and electronics
Move in the next 90 days
- Set a target mix and a limit on exposure to any 1 program
- Qualify shared equipment for both markets
- Price surge capacity at its opportunity cost
Source: Evidence items are facts from the public record as of 18 Nov 2026. Note: The plays are Bastion Atlas analysis.
6. Dates to Watch
Source: Public laws, regulations and company statements listed in Exhibit 12.
| Date | Event | Why it matters |
|---|---|---|
| 11 Dec 2026 | Continuing resolution (P.L. 119-103) expires | A further extension keeps FY2026 rates and, absent a specific exception, the section 102 bar on new starts, production-rate increases and certain new multiyear procurements. |
| 1 Jan 2027 | DFARS 252.225-7052 extends to the full supply chain | The sourcing restriction on samarium-cobalt and neodymium-iron-boron magnets, tungsten and tantalum from China, Russia, Iran and North Korea reaches back to mining and refining, at every contract tier. Exceptions include certain commercial off-the-shelf items and nonavailability waivers. |
| By 3 Jan 2027 | Last window for a reconciliation law in the 119th Congress | Decides whether any of the $350B mandatory request is funded. The House-passed budget resolution limits the Armed Services Committee to $60B of added deficits over 10 years. The Senate has not voted on its version. |
| 3 Jan 2027 | 120th Congress convenes with Democratic majorities in both chambers | New chairs at House and Senate Armed Services (Adam Smith, Jack Reed). Expected oversight topics at House Armed Services: Golden Dome, munitions stockpiles and government equity deals. |
| 10 Jan 2027 | China’s suspension of its October 2025 export controls ends unless extended again | Rare-earth supply and price risk returns. The April 2025 license controls on 7 rare earths stay in force either way. |
| By about 16 Jan 2027 | Supply-chain mapping guidance due under Executive Order 14415 | Shows which contracts must map critical supply chains from the raw material up. Regulations are due within 90 days after the guidance. |
| By 1 Feb 2027 (statutory date) | FY2028 President’s Budget due | Shows whether the FY2027 ramp carries forward. The current out-year path falls to $1.28T in FY2028 without new reconciliation money. |
| Open | New date for CMMC Phase II | The task force review that paused Phase II has not published a schedule. A restart would return third-party certification as a condition of award. |
| Back half of 2027 | 737 at 52 a month and A320 family at 70-75 a month by year-end | Peak commercial pull on shared capacity. |
| 2030 | PAC-3 MSE at about 2,000 a year | End point of the largest munitions framework. Sub-tier capacity must be in place well before. |
Source: Public laws, regulations, bills and company statements.
What would change this view
- Upside: Any reconciliation law, or enactment of the supplemental request, which carries $21B for munitions.
- Downside: A full-year continuing resolution with no exception for the rate increases and new multiyear contracts behind the frameworks.
- Watch: A new Phase II date for CMMC, China’s decision due by 10 Jan 2027, and whether 7-year subcontracts reach below Tier 1.
About This Report
- Scope: US aerospace and defense manufacturing at Tier 1 and below, across defense, commercial aerospace and naval programs. Data cut-off: 18 Nov 2026.
- Evidence base: Department of War FY2027 budget documents, the Congressional Budget Office estimate of Iran war costs, the FY2027 defense authorization and appropriations bills, the 2026 munitions framework announcements, third-quarter 2026 results from the primes, federal rules and proclamations on materials, tariffs and cybersecurity, and studies from Roland Berger, Bain, BCG, the Aerospace Industries Association, Deloitte, Mergermarket and Preqin. SONAR’s continuously updated intelligence layer was the signal source, through the 46 SONAR reports issued between 30 Aug and 18 Nov 2026.
- Verification rule: Every figure met 1 of 2 tests before use. It was read from the primary document where that document is public, or it was confirmed in at least 2 independent accounts of an official announcement or company statement. Headline figures were then checked a second time against the source. This edition also reflects an independent line-by-line fact check, with each challenge tested against the primary document before any change was made. Figures that failed a pass were corrected or removed.
- Request is not appropriation: Unless marked as enacted, FY2027 figures are the President’s Budget request of 3 Apr 2026. Mandatory figures depend on a reconciliation law that has not been passed.
- Company figures: Backlog, guidance, targets and framework agreements are as stated by the companies. Framework agreements remain subject to congressional authorization and appropriations.
- Analysis: The “Bottom Line”, section lead-ins, “So what” notes, planning cases and plays are Bastion Atlas judgment built on the facts above.
Key public documents behind the figures
- Department of War, FY2027 Budget Request briefing and Overview Book (April 2026)
- Department of War, FY2027 Mandatory Funding Overview
- P.L. 119-103, Continuing Appropriations and Extensions Act, 2027 (Division A, section 102)
- Congressional Budget Office, cost estimate for operations against Iran (15 Sep 2026)
- House Appropriations Committee, FY2027 defense bill summaries (June 2026, H.R. 9495)
- H.R. 8800 and S. 4784 (FY2027 defense authorization bills) and H. Con. Res. 113 (House budget resolution)
- Lockheed Martin, RTX, Northrop Grumman, General Dynamics, HII, Boeing and GE Aerospace, third-quarter 2026 results
- Department of War and company announcements of the 2026 munitions framework agreements (January to July 2026)
- Executive Order 14415 (20 Jul 2026) and DFARS 252.225-7052
- China Ministry of Commerce, announcement of 9 Nov 2026 on export-control suspensions
- Department of War, memorandum suspending CMMC Phase II (July 2026)
- Presidential proclamations on Section 232 steel, aluminum and copper duties (2025-2026)
- Roland Berger with GIFAS, BDLI and ADS, The global aerospace supply chain in 2026 (May 2026)
- Bain & Company, 2026 review of 15 aerospace and defense programs
- BCG, aerospace materials lead-time analysis (2024)
- Aerospace Industries Association, workforce study (2025)
- Deloitte and the Manufacturing Institute, manufacturing talent study (2024)
- White & Case and Mergermarket, defense mergers and acquisitions data for the first 9 months of 2026
- Preqin, private capital deal data for aerospace and defense (2025)
- Hadrian, Series D announcement (6 Aug 2026)
- Department of War, FY2027 budget justification for the Office of Strategic Capital loan program (April 2026), and Congressional Research Service IF13215